Eric Wright Group
We provided a full turnkey solution to deliver the necessary electrical connection and effectively power new electric vehicle chargers for Eric Wright Group through our electrical connection upgrades.
A new 3c 300 waveform cable was installed to supply the main building. We installed and terminated three 200A Lucy Zodion pillars, each supporting 16 x 7kW chargers, along with associated earth mats. LV car charger plinths were installed by the appointed civil contractor, who also completed the public highway works.
In addition, we utilised our Option 2 status as an Independent Connection Provider, carrying out all HV and LV on-site cabling and operational duties on the Electricity North West distribution network using our own ENWL-authorised staff, ensuring safety, compliance, and reduced reliance on third parties.