InstaVolt | Stokers Furniture, Chester
For InstaVolt and Stokers Furniture in Chester, Serconnect delivered a full turnkey HV and LV infrastructure package, including the construction of a 1MVA X-Type package substation to support 12 ultra-rapid 160kW EV chargers. The project represented an important milestone for InstaVolt as its first scheme to be delivered using an X-Type package substation through an ICP partner.
Serconnect was appointed to deliver the HV and LV infrastructure for the site, including the construction and installation of a new 1MVA X-Type package substation.
As the first X-Type package substation scheme delivered by InstaVolt through an ICP partner, the project involved close coordination between InstaVolt, the DNO, IDNO and wider project stakeholders.
The technically complex scheme required a collaborative and solutions-focused approach throughout the design, approval and construction phases, with Serconnect working closely with all parties to maintain progress and ensure the project remained on programme.
The scope of works included:
• Construction of a new 1MVA X-Type package substation
• HV electrical infrastructure
• LV electrical infrastructure
• Installation and connection works required to support the EV charging hub
• Coordination with InstaVolt, the DNO, IDNO and wider project stakeholders
• Testing and commissioning
• Final energisation of the site
Throughout the project, Serconnect maintained close communication with the wider project team, responding promptly to challenges and coordinating the technical requirements between the various parties involved.
The team's experience in delivering HV and LV infrastructure through an ICP model helped ensure the project progressed efficiently through the design, approval, construction and commissioning stages.
The completed infrastructure provides the capacity required to support 12 ultra-rapid 160kW EV chargers, helping to expand the availability of high-speed EV charging in the area.
The project also established an important benchmark for InstaVolt's future ICP-delivered X-Type package substation schemes, demonstrating the successful collaboration between InstaVolt, Serconnect, the DNO, IDNO and wider project team.
Throughout the project, the Serconnect team demonstrated a proactive, collaborative and solutions-focused approach. Their engagement with InstaVolt, the DNO, IDNO and wider project stakeholders helped navigate a technically complex scheme whilst maintaining momentum through the design, approval and construction phases.
Tim Douglas, Head of Delivery - InstaVolt